Detention is a charge for keeping carrier equipment outside the terminal beyond the allowed free time. It commonly applies from container gate-out until empty return, or from equipment release until export gate-in.
When does detention accrue?
The contract defines the starting event, free days, return location and counting method. The clock may continue even when a return depot is congested unless relief rules apply.
How is detention calculated?
If seven free days are allowed and an import container is returned on day ten, three chargeable days apply. At $125 per day, the illustrative charge is $375.
Detention versus demurrage
Detention generally concerns equipment outside the terminal. Demurrage generally concerns cargo or containers remaining inside the terminal beyond free time.
How can it be controlled?
Schedule unloading and empty return early, confirm depot acceptance, retain gate receipts and document closures or rejected returns.
What should be reviewed?
Check equipment number, gate-out and return timestamps, free-time entitlement, tariff tier, holidays, depot instructions and evidence supporting any dispute.